5,296.98MW generation capacity recorded in 2024/Q4 amid multiple grid collapse – NERC

 

BY AKUDORO GLORIA

The average generation capacity across the grid-connected plants in Nigeria increasesd by 195.98 mega watts (MW) in quarter four (Q4) of 2024.

The Nigerian Electricity Regulatory Commission (NERC) in its quarterly report for 2024/Q4, noted that generating capacity of generating companies soared from 5,100MW to 5,296.98MW in the period under review.

It also showed that the average hourly generation on the grid in the period was 4,207.41 megawatt-hours per hour (MWh/h), which translates to a total generation of 9,289.95GWh. This represents a decline of 72.83MWh/h (-1.70%) from 4,280.24MWh/h in the third quarter (Q3) of 2024.

The report which covered the months of October, November and December further showed that three (3) incidents of total collapse and two (2) incidents of partial collapse occurred on the national grid.

According to NERC, the partial collapses were recorded on 14th October and 5th November 2024, while the total collapses were recorded on 19th October, 7th November and 11th December 2024, respectively.

It emphasized that the System Operator (SO) is expected to submit to the Commission a detailed report containing the root causes of the incidents leading to the system disruptions and mitigation plans to avoid a recurrence of similar incidents as contained in section 20.1 of the Grid Code.

“In 2024/Q4 the average lower daily (49.39Hz) and average upper daily (50.91Hz) system frequency were outside the normal operating limits (49.75Hz -50.25Hz) but remained within the lower and higher bound stress limits (48.75Hz -51.25Hz). The average lower daily (300.21kV) and average upper daily (349.45kV) system voltage were however outside the limits prescribed in the grid code (313.50kV -346.50kV)”.

The Commission vowed to continue to push the SO to improve its system coordination activities to avert the system risk posed by the continuous operation of the grid outside the normal operating limits.

The quarterly report, according to NERC is in pursuant to Section 34(1)(e) of the Electricity Act (EA) 2023, which states that “the Commission shall ensure the safety, security, reliability and quality of service in the production and delivery of electricity to customers.

NERC said that it will continues to monitor the technical, operational, and commercial performance of the Nigerian Electricity Supply Industry (NESI). The Commission maintained that it will continue to publish quarterly reports that will update the public on the overall performance of the NESI.

“In 2024/Q4, there were twenty-eight grid-connected power plants consisting of 19 gas, five (5) hydro, two (2) steam, and two (2) gas/steam-powered plants.
“For this quarter, the average available generation capacity of the grid-connected power plants was 5,296.89MW.

“The average available generation capacity across the grid-connected plants increased by 195.98MW (+3.84%) from the 5,100.90MW recorded in 2024/Q3 to 5,296.89MW in 2024/Q4.

“Fifteen (15) power plants recorded increased available generation capacities in 2024/Q4 compared to 2024/Q3.

“The average hourly generation on the grid in 2024/Q4 was 4,207.41MWh/h, which translates to a total generation of 9,289.95GWh. The average hourly generation of grid-connected power plants decreased by72.83MWh/h (-1.70%) from 4,280.24MWh/h in 2024/Q3. The total electricity generated in the quarter also decreased by 160.81GWh(-1.70%) from 9,450.76GWh in 2024/Q3 to 9,289.95GWh.

“The decrease in generation during the quarter was primarily due to the decrease in energy offtake by the
by the grid-connected customers (including DisCos) compared to
2024/Q3,” it explained.