Poised by the determination to guarantee increased electricity supply throughout the nation, the Transmission Company of Nigeria (TCN) has commissioned the installation of 100MVA 132/33kV power transformer at its Port Harcourt main substation.
This is coming a week after the Company had commissioned 100MVA 132/33kV power transformer at Dan Agundi Transmission Substation in Kano State sequel to the fire incident that engulfed its substation in the region.
Amidst challenges in gas supply for power generation leading to low generation output, the TCN had reported that previously, the Dan Agundi substation had been operated by three units of 60MVA capacity transformers. But after the unfortunate fire incident that resulted in the damage of one transformer with partial effects on another, the substation capacity was reduced to one 60MVA transformer while the load allocation stood at 30MW.
However, the TCN in a statement issued on Tuesday 19th March 2024, by the GM, Public Affairs, Mrs. Ndidi Mbah, revealed that the 100MVA transformer installed at its PortHarcourt substation will enhance the bulk transmission capability of the substation by 80MW.
According to the statement, this initiative, which is a TCN-World Bank project, also includes the complete rehabilitation and expansion of the 132/33kV transmission substation.
This its said also include the addition of three feeders and associated accessories.
“With the installation of the 100MVA power transformer, the substation’s installed capacity increased from 180MVA to 280MVA. Notably, industries in the Trans Amadi industrial environment and communities beyond Port Harcourt city will benefit significantly from this capacity expansion.
“Within the first quarter of this year, TCN has executed a number of projects in its Port-Harcourt Region, and currently has several ongoing projects which are at various completion stages, including a 100MVA transformer installation in Port Harcourt Town which will soon be completed and commissioned.
“Transformer projects are equally ongoing in Port -Harcourt Town, Itu, Umuahia, Aba, and Alaoji, aimed at bolstering bulk power transmission within the region”, the statement revealed.
Furthermore, in its Port Harcourt Sub-region, TCN said had recently received four power transformers including two units of 100MVA capacity transformers, one each at Port Harcourt Main and Port Harcourt Town transmission substations, two units of 60MVA power transformers, one each were also sent to Rumuosi and Port Harcourt Main transmission substations.
Collectively, these will increase available capacity within TCN’s Port Harcourt region for Port Harcourt Distribution Company to offtake for its customers, according to the statement.
Its further disclosed an ongoing upgrading of the Itu substation at the Uyo Work Centre with a 60MVA 132kV transformer and associated switch gears which upon completion, the station’s capacity will increase by 48MW.
TCN clarified, “Ongoing new substation projects within the region include the construction of a 2x60MVA 132/33kV transmission substation at Oron and a 2×30/40MVA 132/33kV Substation at Ididep both in Calabar.
“To increase maintenance efficiency and invariably reduce downtime, the Regional Store received bulk consignment of spare parts, including circuit breakers, 33kV lighting arresters, battery chargers, battery banks, toolboxes, and safety kits”.
TCN therefore reaffirmed its steadfast in its effort to put in place a robust and more efficient transmission grid through strategic initiatives and project implementation across regions. Adding that its committed to swift maintenance and fault response by ensuring it has available, necessary spare parts in its stores nation.