Aba power recovers 50MW affected by TCN ongoing maintenance 

 

… set to commission special lines for manufacturing companies
BY AKUDORO GLORIA 
Aba Power Distribution Company has activated a new 47 megawatt (MW) General Electric turbine in its embedded power plant in the Osisioma industrial area of Aba to compensate for a 50MW loss.
This development came in less than 48 hours after the Disco assured electricity consumers in the Aba Ringfence, comprising nine of the 17 local government areas in Abia State, of its readiness to start supplying it’s coverage areas affected by the ongoing maintenance of Transmission Company of Nigeria (TCN) facilities in the state.
The DisCo who made this known in as statement signed by its Brand and Communication Manager, and communication, Edise Ekong, said it is now supplying more power to communities, businesses and households within its ringfence.
“The good news is that we have kept our word.
“The better news is that we are now supplying more power to communities, businesses, and households in our ringfence, making the TCN maintenance of its facilities more or less a blessing in disguise for our customers.
“Following the one-week maintenance outage by TCN, which began on Monday, Aba Power, Nigeria’s 12th DisCo, would not be able to receive bulk electricity from the Niger Delta Power Holding Company (NDPHC) from 9 am to 5 pm daily, a development that put several communities in darkness the first day,” it stated.
Ekong attributed the outage in places like IGI feeder, Ukwa Feeder, among other to TCN’s failure to respond early enough to Aba Power’s request to start supplying power from the Geometric Power’s 188MW gas-fired power plant in the Osisioma Industrial Zone in Aba.
He continued, “We are glad that when the TCN eventually granted us permission the next day to start supplying power to the affected areas, we not only recovered the lost supplies but are now giving Aba people more electricity than before the repairs and maintenance began.”
Ekong commended the NNPC Gas Marketing Company Limited (NGML) and its partner, Heirs Energies, for acceding to the request for steady gas supply to the embedded power plant, which made the plant kick start another 47MW General Electric (GE) turbine immediately.
He added, “We still receive supplies from the NDPHC through the TCN between 5 pm and 8 am daily, hence more electricity to all parts of the Aba Ringfence except areas with special problems like vandalism and failed, obsolete, and unserviceable machines which are now being replaced.”
This is also as the Communication Manager revealed that Aba Power is building special lines for big manufacturing companies like Nigerian Breweries and Seven-Up Bottling plc.
“Once we commission the Factory, Ogbor Hill, and Owerrinta lines this month and next, the industries in Aba will experience drastically reduced production costs because they will no longer have cause to self-generate electricity, one of the most significant contributors to high business costs in Nigeria,” he stated.
Meanwhile, a mechanical engineer and notable electricity consultant in Abuja, Dike Ejike, has advised other DisCos to emulate the Geometric Power Group. He emphasized the importance of providing constant, quality, safe, and affordable electricity for consumers.
Mr. Ejike stressed on the need for the DisCos to invest substantially in the business before expecting a profit.
“It is concerning that most of those who emerged as the core investors in the 11 DisCos created out of the Power Holding Company of Nigeria (PHCN) did not know anything about the power business, nor did they have the technical or commercial competence.
“They merely used their government connections in 2023 to grab our collective patrimony, this the ongoing crisis in the electric power sector. They need to learn from Aba Power,” he lamented