North-East states comprising Adamawa, Borno, Taraba and Yola, have been plunged into total darkness to enable the Transmission Company of Nigeria (TCN) install new towers in the region.
The power outage which commenced at 10:00am on Tuesday, June 10, is expected to last until 5:00pm on Saturday, June 14.
According to the Management of Yola Electricity Distribution Company (YEDC), the planned outage is to enable TCN carryout major installations on the Jos-Gombe 330kV and Jos-Bauchi-Gombe 132kV transmission lines, involving the installation of new towers at the Bauchi 330kV station and the crossing of the existing 132kV line.
“During this time, Damaturu, Molai, Yola, and Jalingo injection substations will be out of supply.
“Biu will be supplied from alternative sources, namely the Dadin Kowa Hydro Plant, while Baga Road substation in Maiduguri will be back-fed from MEPP. Nguru, Machina and environs will also be fed through the 33kv Nguru feeder.
“Please note that this is a TCN-led activity and YEDC is working in alignment to support the ongoing efforts aimed at strengthening the regional transmission network. Normal supply will be promptly restored upon confirmation that the work is completed,” the statement read.
The DisCo therefore, expressed gratitude to customers within the region for their patience and understanding during this period.