FROM SUNDAY MATTHEW TAGGAH, KADUNA
The Kaduna State Government has said that its ongoing road rehabilitation and new construction projects will revive moribund industries, reopen closed businesses and significantly ease transportation across industrial corridors of the state.
Managing Director of the Kaduna Roads Agency (KADRA), Dr. Abdullahi Baba Ahmed, disclosed this during an inspection tour of projects in the Kakuri industrial layout, Barnawa, Pan Drive-Television Road and the Raba-Rigasa train station dual carriageway.
Ahmed explained that many of the projects were inherited from the previous administration but had stalled due to outstanding certificates, unpaid compensations and issues relating to the relocation of water and electricity lines. He said Governor Uba Sani revived the projects by clearing “huge financial liabilities,” ensuring contractors returned to site.
“We inherited this Kakuri-Nasarawa-Flour Mills road at 25 per cent. Only drainage was partly done — no stone base, no binder, no asphalt. Today, we are at 65 percent and the binder course has been laid. This road passes through an industrial layout where businesses had shut down. With work now progressing, industries are returning to life,” he said.
He also noted that close to one billion naira in compensation had been released for about 120 households affected by the Raba-Rigasa road project.
Describing the Raba-Rigasa train station dual carriageway as one of the state’s most critical road projects, Ahmed said it provides a major link from Arewa House through Mahuta to the train station. According to him, the project was inherited at 30 per cent completion but has recorded significant progress following major drainage works and binder layers already executed.
“This is a dual carriageway that will ease movement to the Rigasa station and beyond. His Excellency insisted it must be delivered before the next rainy season. These are not just asphalt and concrete — these are roads to progress. They will reopen closed businesses,” he added.
On the Kabala–Aliyu Makama–Barnawa dual carriageway, the KADRA boss confirmed that asphalt has been laid and bridge components are already underway.
Project Manager of CCECC Kaduna Office, Henry Zhang, also affirmed the pace of work, saying more than 30 per cent of the Raba road project has been completed. “We have achieved milestones on Raba Road. We completed three kilometres of stone base and binder course. With continued support, we will finish as soon as possible,” he said.
Residents, who spoke during the tour expressed gratitude to the governor, with some pledging support for his second term.
Moses Haruna, a resident of the Television area, commended the speed of work. “We have seen everything going on and we the Southern Kaduna youths are ready to contribute money to buy him a form for his second tenure. They told us successors are usually worse, but Uba Sani is different. Uba Sani is the best,” he said.
Another resident, Ladidi Abubakar from Kabala, described the road as a major relief. “Before, the road was in deplorable condition, but now it is very good. We appreciate our governor for the work he is doing,” she said.
KADRA assured that work will continue across the state as weather conditions permit.