Umahi Threatens To Terminate Lokoja–Benin Road Contract Over Slow Pace

By Joy Onu

The Minister of Works, David Umahi, has warned contractors handling key federal road projects, particularly along the Lokoja–Benin corridor, insisting that underperformance will no longer be tolerated and that delays must not be linked to President Bola Ahmed Tinubu’s administration.

The Minister delivered the caution on Tuesday during an inspection tour of major road and bridge works across Kogi and Edo States, with particular attention on the deteriorating and slow-moving sections of the Lokoja–Benin dual carriageway. The corridor, regarded as one of the country’s most critical transport arteries linking the North and South, formed the central focus of his assessment as concerns mounted over its pace of rehabilitation.

Expressing dissatisfaction with the progress recorded on some portions of the Abuja–Lokoja dual carriageway and the Obajana Junction–Benin road dualisation, Umahi said the gap between reported progress and the reality on ground was unacceptable. He disclosed that funding limitations had already forced a reduction in scope on one section of the Abuja–Lokoja road, scaled down from 49.28 kilometres to 28 kilometres to prioritise critical segments.

“I am very sad with what I saw on the ground. What was reported to us is not reflected in the actual work being done,” he said, warning that such discrepancies would attract strict consequences.

On the Lokoja–Benin axis, where multiple contractors are currently active, the Minister stressed that the Federal Government would no longer accept prolonged road closures beyond 14 days during construction. He cautioned that any contractor who failed to comply with the directive risked outright termination of their contract, noting that Nigerians deserved uninterrupted access even during rehabilitation works.

He further issued a 72-hour ultimatum to GELD Construction Company, which is handling one of the sections, directing the firm to immediately demonstrate visible progress by properly deploying funds already released to the project.

In contrast, Umahi commended JRB Construction Company for what he described as commendable performance, citing the quality and speed of work as evidence that efficiency was possible when contractors adhered to specifications. “If everybody does his job accordingly, there will be no reason to shift the blame to Mr. President,” he added.

The Minister also reviewed ongoing works being executed by Trucrete Solutions Limited along the Koton Karfe–Abuja alignment, as well as other bridge interventions and dualisation projects spanning Kogi and Edo States. At several points along the corridor, he reiterated that federal highways must not be left in prolonged disrepair under the guise of project execution.

Particularly on the Obajana Junction–Okene–Auchi stretch, which forms a major part of the Lokoja–Benin dualisation project, Umahi directed engineers, Federal Controllers of Works, and project supervisors to tighten monitoring processes and ensure that contractors are held strictly accountable for both timelines and quality standards.

He also inspected flyover and interchange components handled by CCG Contractors, where the flyovers were reported at about 80 per cent completion, while the interchange component stood at roughly 30 per cent.

Reinforcing the Federal Government’s position, Umahi maintained that President Bola Ahmed Tinubu inherited a heavily deteriorated road infrastructure system but has continued to prioritise its rehabilitation through sustained investment and policy direction.

Backing the Minister’s position, the Chairman of the Senate Committee on Works, Allwell Heacho Onyesoh, commended what he described as a firm and result-driven approach to project supervision. He noted that political office holders could no longer continue to absorb public criticism for contractor inefficiency, stressing that delivery timelines must now be strictly enforced.

Similarly, the Chairman of the House Committee on Works, Akin Alabi, urged stakeholders to support the Ministry’s reform-driven approach, describing road infrastructure as a shared national responsibility. He also assured contractors that the Federal Government remained committed to fulfilling legitimate payment obligations, while praising firms showing commitment to delivery standards.

Meanwhile, the Managing Director of GELD Construction Company assured the inspection team that the firm would intensify efforts on its assigned sections in line with the Ministry’s expectations, pledging improved performance in the coming weeks.

The Federal Ministry of Works reaffirmed its resolve to enforce accountability across all ongoing road projects nationwide, warning that underperforming contractors would face sanctions, including possible contract termination, as the government intensifies efforts to deliver durable and timely road infrastructure, particularly along the strategic Lokoja–Benin corridor.