Wike Seeks Federal Funding To Complete Abuja Millennium Tower, Says Cost Tops N400bn

By Joy Onu

The Minister of the Federal Capital Territory (FCT), Barrister Nyesom Wike, has attributed the prolonged delay in completing the Abuja Millennium Tower to the enormous funding required for the project, saying the estimated cost of more than ₦400 billion is beyond the capacity of the FCT’s statutory budget.

Wike said this on Thursday after inspecting key infrastructure projects across the Federal Capital Territory, where he also reaffirmed the administration’s commitment to completing all ongoing road projects scheduled for delivery before the end of 2026. The minister’s position was contained in a statement issued by the Deputy Director of Press, Office of the FCT Minister, Rabi Musa Umar.

He said the FCT Administration was in discussions with President Bola Ahmed Tinubu to have the Millennium Tower designated a national project and major tourist destination eligible for Federal Government funding.

“That is a national project. I believe it is one project that the government should reconsider as a tourist center project. The capital involved is too huge for the FCT’s statutory budget. As I speak to you, the contractor is talking about not less than ₦400 billion. If we attempt to carry out such a project alone, every other project in Abuja will be abandoned. But we are discussing with the President to consider it as a national project,” the minister said.

The Millennium Tower, conceived as one of Abuja’s signature landmarks, has remained uncompleted for years despite repeated efforts by successive administrations to revive the project.

During the inspection, Wike visited the extension of Collector Road CO1 in the Institution and Research District, stretching from Nile University to Ring Road III, including the extension from Baze University Junction. The project is expected to improve connectivity for major academic, legal and research institutions within the district. He also inspected the Arterial Road N1 linking Wuye District to Ring Road II.

The Minister said the projects were designed to ease traffic congestion, stimulate economic activity and strengthen Abuja’s infrastructure as part of efforts to develop the capital into a world-class city. He expressed satisfaction with the quality and pace of work on the Collector Road CO1 project.

Providing an update on the Arterial Road N1 being executed by Arab Contractors, Wike assured residents that the project would be completed and formally handed over before the end of the year.

He said the steady progress on the projects reflected the confidence contractors had in the government’s commitment to meeting its financial obligations.

“For me, it’s the confidence in us by the contractors. Even if we have not fully met our obligation at any point, they still go ahead knowing fully well that we will fulfill our part. That trust is there, and I am highly elated with the level of work,” he said.

The minister added that the FCT Administration was simultaneously completing legacy projects awarded as far back as 2010 while executing new infrastructure initiatives introduced under the administration of President Tinubu.

He appealed to residents to remain patient as work continues across the territory and urged the media to accurately report what he described as the visible transformation taking place in the nation’s capital.