COVID-19, Poor Funding Stall Abuja-Light Rail Project

Two years after President Muhammadu Buhari inaugurated the first phase of the Abuja Light Rail Project with fanfare, New National Star investigations have revealed that works on the remaining nine stations due to open in 2020 have hit a brick wall due to the COVID-19 pandemic and poor funding.

The first phase, which was launched in July 2018, connects the city centre to the Nnamdi Azikiwe International Airport, stopping at the Abuja-Kaduna Railway Station, Idu. When the project was launched with the promise of delivering the remaining nine stations in two years, residents and workers who commute to the city daily breathed a sigh of relief. However, as the year draws to a close, the earlier euphoria of having an effective mass rail transit system has waned among members of the public.

The 42.5 km (26.4mi) first phase has two lines and 12 stations and the entire proposed 290 km (180 mi) network being handled by China Civil Engineering Construction Corporation is to be developed in six phases at an estimated cost of US $824 million, with 60% of the cost to be funded by loans from the Exim Bank of China and 40% from the Federal Capital Territory Administration (FCTA). The mass rapid transit is first of its kind in West Africa and the second of such system in Subsaharan Africa after the Light Rail system in the Ethiopian capital Addis Ababa.

The Abuja Light Rail is intended to tackle transportation problems and traffic congestion which are surging in the Federal Capital Territory (FCT) Abuja. A cross-section of residents who spoke on the government’s failure to deliver on the project expressed fears that it may just become an addition to failed projects in Nigeria.

A taxi driver, Mr Charles Enoh, speaking on the light rail said he did not think it would commence full operation anytime soon. According to Enoh, two years after the inauguration of Abuja Light Rail ‘‘we are still foot-dragging on it, this is very sad and it appears it may not be feasible before another administration comes in.’’ For his part a civil servant, Mr Ihemefuna Osita said, “ The Abuja Light Rail is a groundbreaking project for Nigeria. Personally, I have long awaited the use of the facility, if put to use adequately, it will reduce road accidents and make transportation easier. People welcomed the project with excitement, now it has been inaugurated and we are unable to access it.”

Another respondent, Barr Dayo Ariyo, who stays around Kubwa and comes to work in the central business area told this newspaper that “the benefits of the Abuja Light Rail to everyday commuters are enormous. People will be relieved from the high costs of road transportation which keep fluctuating due to the price of fuel but the issue is how to access the light rail. As the infrastructure has not gone round to cover everywhere.” Efforts to reach the Director of FCTA Transport Secretariat, Engr. Tony Agwaniru, for comment on the matter, proved abortive as attempts to reach him through phone and in person yielded no results. However, a source in the Secretariat who pleaded anonymity, told this newspaper that it is a delicate matter and people are scared of talking about it. He said, “Lack of funds is the bane of the project.

‘‘The project was segmented into lots because of the financial implications. Lots 1A & 3 have been inaugurated, it is not possible to do all the lots at the same time. The first phase of the project connects the city centre to the Nnamdi Azikiwe International Airport, stopping at the Abuja-Kaduna Railway station in Idu.”

“The railway line is planned to stretch for 290 kilometres. This would cost $824 million with an additional $194 million which would be provided by China’s Exim Bank for the supply of 48 coaches as well as maintenance for three years,” he added. The project which began in 2007, November 30th – 6th December, 2020 during Olusegun Obasanjo’s Administration will link 13 communities with 12 stations namely Abuja Metro, Stadium, Kukwaba 1 and 2, Wupa, Idu, Bassanjiwa, Airport, Gwagwa Dei-Dei, Kagini and Gbazango. When contacted, Malam Sani Abubakar, Special Assistant Media and Publicity to the FCT minister, said “since the President inaugurated it, it has been running but work has stopped due to the Covid-19 pandemic” Abubakar said that being a commuting train service it covered short distances, noting that the highest distance it would l go when fully operational is Kubwa. He said maybe before the end of the year work would recommence.

According to him “recently, FCTA acquired two more coaches for the commercial operations but it is being sorted out. In total, 48 coaches are being expected. There are 12 stations along the route, when it becomes fully commercial, it will drop passengers at the 12 stations.

‘‘For now, it stops at 3; which is Metro metro, Idu and Airport. Idu is a Terminus, we have the section for FCT Abuja Light Rail and a section for Nigeria Railway Corporation (NRC) which runs the Abuja – Kaduna train service. When the stocks arrive, actual commencement of mass transport will begin. Works are being done to ensure the completion of other phases of the project.”