Bureau of Public Procurement (BPP) has issued comprehensive guidelines for
the implementation of the Federal Government’s revised policy on contract
variations and mandatory use of final designs for public projects. This is
contained in a statement issued by Zira Nagga, Head of Press and Public
Relations, BPP, in Abuja on Saturday. According to the statement, the
guidelines, issued pursuant to Sections 5(a) and (o) of the Public Procurement
Act (PPA), 2007, follow the approval of the revised policy by the Federal
Executive Council (FEC).
The statement said the policy was conveyed through the Office of the Secretary
to the Government of the Federation (SGF) Circular Ref. No. 59780/S.2/B/568
dated December 2025, adding that the new framework centralises the review
and certification of all requests for revision of contract sums and modification
of contract scope under the BPP. “The latest guidelines supersede the 2013
circular which required Presidential approval for Revised Estimated Total Cost
(RETC) and variations above 15 per cent of the initial contract sum or N1
billion.”
The statement explained that under the revised framework, the applicable
Service-Wide Prior Review and Monetary Thresholds would determine the
appropriate approving authority for variations and scope modifications.
It added that all Ministries, Departments and Agencies (MDAs) were now
required to submit requests for variation orders, fluctuation claims and scope
modifications directly to the BPP for review and certification.
The statement
said no variation or fluctuation claim would proceed to the relevant approving
authority without a BPP Certificate of No Objection and said that the guidelines
were designed to ensure transparent and legally-compliant procedures for
processing contract variations, while protecting public interest and promoting
accountability, value for money and timely project delivery. “Variations will
only be approved where they are genuinely necessary, could not have been
foreseen with reasonable diligence, and do not fundamentally alter the original
scope of the contract. “Unit rates for varied works must be consistent with the
original contract rates,” it added.
The statement also listed permissible grounds for variation to include
unforeseen site conditions, material errors in design and Bills of Quantities
(BOQ)/Bills of Engineering Measurement and Evaluation (BEME), statutory or
regulatory changes after contract execution. “Others are significant price
escalation caused by macroeconomic shocks or force majeure, and value
engineering improvements that reduce cost without altering scope.”
It, however, warned that variations arising from inadequate planning, avoidable
design flaws or addition of new components not contemplated in the original
scope would not be accepted. “Such additions must be procured as separate
contracts,” it stated.
The statement further clarified the distinction between variation and fluctuation
claims, noting that fluctuation claims related to changes in the cost of labour,
materials and exchange rates must be handled strictly in line with the conditions
of the contract. It warned that contractors who deliberately delayed projects to
generate fluctuation claims would be denied such claims and could be debarred
if the claims were found to be bogus or overstated. It further directed that all
procurements must be based on approved final designs to reduce avoidable
variations. Also, according to the statement, the use of preliminary or flawed
designs that lead to unnecessary variations will attract regulatory sanctions.
On approving thresholds, the statement said augmentation or variation sums,
rather than the total revised cost, would determine the approving authority. It
explained that works variations of N10 billion and above would require
approval by the FEC or National Judicial Council (NJC) or National Assembly
(NASS) Tenders Board. “While variations between N5 billion and below N10
billion would go to Ministerial Tenders Boards/NASS and works variations of
between N75 million and below N5 billion would be handled by Parastatal or
Judicial Tenders Boards. “Variations below N75 million for works and N50
million for goods and services would be approved at the accounting officer
level”, adding that BPP Certificate of No Objection constituted regulatory
clearance to proceed to the approving authority but did not amount to approval
for payment