Delta Govt Awards N78bn Effurun, Environs Beautification Contracts

By Chris Awhawha, Warri

Governor Sheriff Oborevwori of Delta State on Tuesday approved the award of contracts worth N78 billion for the construction of three flyover bridges and road expansion to beautify Effurun and  Warri environs.

The contracts awarded to Julius Berger Nigeria Limited has 27 months tenure to reshape and beautify Enerhen junction, a section of DSC/NPA expressway,  Effurun roundabout and PTI junction all in Uvwie Local Government Areas of the state.

This decision which was taken at the State Executive Council meeting presided over by Governor Oborevwori on Tuesday in Asaba, has excited Deltans, especially residents in Effurun and Warri axis.

Permanent Secretary in the Ministry of Works, Engineer Fred Edafiogho, while announcing this to journalists, said the approval followed the commitment of government to resolve the gridlock often experienced in the twin cities.

“The contracts include the design and construction of flyover bridge at Enerhen junction to Marine Gate; study, design and construction of road expansion and improvement works on the section of the DSC/NPA Expressway from Effurun roundabout to DSC roundabout including construction of a 3/4 Cloverleaf interchange at the existing Effurun Flyover Bridge as well as two pedestrian bridges.

“Others are design and construction of flyover bridge at PTI junction and DSC roundabout along the Effurun/Patani, East-West highway, Effurun in Uvwie Local Government Area,” the Permanent Secretary noted.

Edafiogho further said that the project road expansion works on the DSC/NPA Expressway will provide two lanes of restricted carriageway at the centre for through-traffic and another two lanes of service road in each travel direction bring the current capacity of the road from four lanes to eight lanes.

“Side drains would be provided along the stretch to convey storm water to the swamp that runs beside the road and pipeline in addition to provide free flow of traffic for a distance of 4.359km with cloverleaf interchanges and U-turns allowing for unimpeded flow,” he said.

He further added that the four projects have a duration of 27 months with probable completion date of December 2025.

Also, the Commissioner for Works, (Highways and Urban Roads), Comrade Reuben Izeze said Governor Oborevwori’s approval of the projects was in fulfillment of his promise to give Warri/Uvwie a face lift.

He noted that the justification for choosing Julius Berger was due to their experience and competitive pricing in relation to the quality of works and timely delivery of projects.

The State Commissioner for Finance, Chief Fidelis Tilije who disclosed that that the contract is worth N78 billion and the state government would make 25 percent advance payment of N19.5 billion with the balance paid through an ISPO for 30 months.

Mr. Charles Aniagwu, the Commissioner for Works-Rural and Riverine Roads, said that Governor Oborevwori was deeply worried about the deplorable nature of federal roads across the state.

“The State Executive Council also directed the Ministries of Works (Highways and Rural Roads) to carry out remedial works on federal roads, particularly the Asaba-Benin Expressway and the Agbor-Eku Road with a view to making them more motorable for road users in the state.”