By SIMEON OGOEGBULEM
The Nigerian Electricity Regulatory Commission (NERC) said that Electricity Distribution Companies (DisCos) operating in the country installed 350,270 meters in the Second Quarter of 2026. The commission disclosed this figure in its 2026 second-quarter report, released in Abuja on Monday.
According to the commission, the 350,270 meters installed in the quarter under review was reduced by 76,715 meters representing a 17.97 per cent drop from the 426,985 meters installed in the first quarter of 2026.
NERC in the report said that 205,486 meters were installed under the Distribution Sector Recovery Programme (DISREP) framework while 123,833 meters were installed under the Meter Asset Provider (MAP) framework and 13,028 meters were installed under the Meter Acquisition Fund (MAF) framework.
It added that 7,643 meters were installed under the Distribution Companies (DisCos) Financed framework, and 280 meters were installed under the Vendor Financed Framework.
The report showed that at the end of June, 7,743,839 out of the total 12,589,486 active registered customers in the Nigerian Electricity Supply Industry (NESI) were metered.
“As of the end of June 7,743,839 out of the total 12,589,486 active registered customers in the NESI were metered, translating to a metering rate of 61.51 per cent,” it said
”To protect unmetered customers from exploitation, the commission said it has continued to issue monthly energy caps for all feeders in each DisCo for states that have not transitioned.”it said.