Despite the fact that Electricity meters are supposed to be free, consumers have continued to grapple with overbilling from Distribution Companies (DisCos) due to inadequate metering, with a report stating that over N64.5 billion was made for meters in 2024.
According to the 2024 Annual Report by the Nigerian Electricity Regulatory Commission (NERC), consumers paid for 508,103 meters under the Meter Asset Provider (MAP) scheme out of the 572,055 deployed during the year.
The price of meters varied depending on the DisCo, with the cheapest single-phase meter costing N127,000.
This occurred despite the DisCos collectively receiving N1.5trn from the N2.1trn they billed their customers in the same year.
This N64.5bn does not include the N10,000 typically charged for application forms or another N10,000 unofficially collected by staff as a “facilitation fee” to expedite meter deployment.
While the report did not state how many meters each disco disbursed during the year, a brief analysis it provided showed that the MAP framework accounted for 88.82 percent of the total installations during the year with Ikeja (131,263 meters), Ibadan (108,071 meters) and Abuja (79,069 meters) DisCos recording the highest number of meters installation. Kano (1,846) and Yola (831 meters) recorded the lowest meter installations.
By these figures, customers of Ikeja Electric paid at least N16.7bn for meters, Ibadan customers paid N13.7bn, and Abuja customers paid N10bn.
Although providing meters is the statutory responsibility of DisCos, the federal government through NERC has continued to shift the burden to consumers, citing the DisCos’ lack of capital.