By Ogana Cyril, Abuja
National Agency for Science and Engineering Infrastructure (NASENI) has dismissed reports by two online media platforms alleging financial impropriety in the award and execution of its ongoing NASENI Campus Project, describing the publications as false, misleading and malicious.
The agency stated this in a statement issued by the Agency Director of Information, Mr. Olusegun Ayeoyenikan and made available to journalist in Abuja on Tuesday, NASENI specifically faulted reports published by Sahara Reporters and Secret Reporters, which questioned the payment of N10.648 billion to CGC Nigeria Limited as mobilisation for the construction of the NASENI Campus project located at the Abuja Technology Village, Lugbe, Abuja.
According to the Agency, the reports wrongly insinuated that the payment, representing 30 per cent of the contract sum, was hurriedly made in December 2025 to exhaust available funds.
NASENI explained that the allegation was entirely unfounded, noting that the mobilisation payment complied fully with existing procurement laws and financial regulations governing public contracts in Nigeria.
The Agency further criticised Sahara Reporters for citing the former 15 per cent mobilisation limit under the Public Procurement Act 2007, stating that the media platform overlooked amendments introduced through the Finance Act 2020, which increased the maximum allowable mobilisation fee for public contracts from 15 per cent to 30 per cent.
NASENI expressed disappointment that both media organisations allegedly failed to seek clarification from its management before publishing the reports, thereby denying the public a balanced and factual account of the project.
Providing details of the project, NASENI stated that the Campus Project is a flagship Science, Technology and Innovation Complex designed to strengthen Nigeria’s innovation ecosystem.
The Agency explained that in 2025, it engaged reputable and qualified firms through a competitive procurement process for the execution of the project. Following the evaluation process, CGC Nigeria Limited emerged as the successful contractor after meeting all technical and financial requirements and obtaining a Bureau of Public Procurement (BPP) Certificate of No Objection.
NASENI noted that the contract award subsequently received approval from the Federal Executive Council (FEC) in November 2025.
The Agency also disclosed that before the mobilisation payment was made, CGC Nigeria Limited provided an unconditional bank guarantee from a reputable Nigerian commercial bank in compliance with approved procurement procedures.
According to NASENI, the contractor was thereafter mobilised with 30 per cent of the contract value to facilitate commencement of work on the project site, stressing that the payment was fully supported by law.
Citing provisions of the Finance Act 2020, NASENI explained that the legislation amended Section 35 of the Public Procurement Act 2007 to permit mobilisation fees of up to 30 per cent for contractors, provided such payments are backed by an unconditional bank guarantee or insurance bond acceptable to the procuring entity.
The Agency quoted the amended provision, which states that “a mobilization fee of not more than 30% for contractors may be paid to a supplier or contractor supported by an unconditional bank guarantee or insurance bond issued by an institution acceptable to the procuring entity until the mobilization fee is fully amortised or recovered.”
NASENI maintained that all procedures relating to the award and execution of the Campus Project were carried out in strict compliance with statutory, legal and procurement requirements.
The Agency urged media organisations to verify information and seek clarification from relevant authorities before publishing allegations capable of misleading the public, reiterating its commitment to transparency, accountability and due process in the execution of public projects.
NASENI follows all due process in awarding public contracts as stated in Finance Act, 2020, which amended the Procurement Act, 2007.
According to the statement, It is on record that the NASENI Campus construction is steadily progressing. The Campus is being developed to address a critical challenge: helping promising Nigerian ideas move beyond research and prototypes into market-ready products, businesses and industries.
When completed, the Campus will provide research laboratories, advanced prototyping and fabrication facilities, co-working spaces and collaborative learning facilities where innovators, researchers, engineers and industry can work together.
The project reflects NASENI’s 3Cs of Creation, Collaboration and Commercialization, providing a pathway for innovators, including those emerging from initiatives such as #InnovateNaija, Futuremakers and others to develop, test and advance their solutions towards the market.
As construction progresses, each milestone brings NASENI closer to creating the infrastructure needed to turn homegrown innovation into economic and industrial value.