Several communities in Kaduna State are currently enduring electricity outages due to vandalism, severe downpour and windstorm that resulted in the collapse of a transmission tower.

According to the Transmission Company of Nigeria (TCN), in a statement signed by General Manager, Public Affairs, Ndidi Mbah, tower No. 7 along the Kaduna town line I and II in Rigasa community collapsed on Thursday, September 18, 2025.

The collapsed disrupted transmission of bulk power to some Kaduna Electricity Distribution (KAEDCO) load centers, particularly those supplying power to parts of Kaduna South.

Kaduna Disco had earlier appealed to its affected customers, noting that outage currently being experienced is due to a collapsed 132kV transmission tower and has affected supply to the Kaduna Town Transmission Station.

TCN revealed that while its linesmen were inspecting the site of the incident, they discovered that vandals had carted away some of the tower members, making it susceptible to collapse.

“The incident primarily affected power supply to parts of Kaduna South, causing power interruption in some communities.

“However, to ensure that the impact of the incident is curtailed, TCN has advised Kaduna Electricity Distribution Company (KAEDCO) to link its 33kV Mogadishu feeder with 33kV Abakwa feeder to enable electricity customers in Mogadishu have access to power supply,” TCN stated.

Areas such as Kinkinau,

Yan Tukwane, Kabala West, Unguwan Muazu and Kaduna North are unaffected by the incident and therefore have normal power supply.

The company noted that its engineers are already at the site of the incident, dismantling the collapsed tower members to enable them clear the site and commence the re-erection of a new tower.

TCN apologized for the inconvenience the incident has caused the affected customers in Southern Kaduna, and acknowledged their patience and understanding as it continues to work round the clock to build a new tower.

“Please note that every effort is being made to minimize the duration of the outage,” TCN affirmed.

As at the time of filing this report, New National Star investigation showed that power had not been restored to the affected communities.