The Transmission Company of Nigeria (TCN) said it has energised two newly installed power transformers at its 330/132/33kV Birnin Kebbi Transmission Substation in Kebbi State.
A statement by the TCN General Manager, Public Affairs, Ndidi Mbah, stated that the 100MVA and 150MVA transformers were energised at 1:18 pm and 2:56 pm, respectively, on Friday, June 27, 2025.
Mbah said the additional transformers have increased the substation’s capacity from 300MVA to 450MVA. Consequently, Kaduna Electricity Distribution Company now has an additional 120MW of bulk power for distribution to its customers across Kebbi, Sokoto, and surrounding areas.
This development, the GM explained, enables TCN to ensure normal bulk power supply to Niamey, Niger Republic.
Mbah reaffirmed TCN’s commitment to the continued expansion and maintenance of the nation’s transmission system, as well as to ensuring a more effective and efficient bulk power transmission nationwide.