BY AKUDORO GLORIA
The Transmission Company of Nigeria (TCN) has announced that the two transformers at the Benin Transmission Substation and Ihovbor Work Centre that were removed for upgrade last year have been successfully upgraded and energized.
This was made known in a statement signed by TCN General Manager, Public Affairs, Ndidi Mbah on Monday.
The Company disclosed that the 132kV Benin Transmission Substation was completed and energized with a new 100MVA 132/33kV power transformer on Saturday, 3rd of February, 2024 and another 100MVA power transformer for the Ihovbor Work Centre energized on the 29th of January, 2024.
TCN emphasized that the energized transformer at Ihovbor 132/33kV Work Centre will provide increased bulk power supply to Benin Electricity Distribution Company (BEDC) for onward supply to Egba, Oluku, Ihovbor and its environs, while the other newly energized 100MVA transformer at Benin Transmission Substation will increase the substation’s capacity from 240MVA to 300MVA.
TCN also pointed that before the recent upgrade, the Benin Transmission Substation had two 60MVA, one 80 MVA, and one 40MVA 132 /33kV Mobitra transformer which was upgraded to 100MVA power transformer whilst Ihovbor had 2x60MVA of which one has been upgraded to 100MVA.
“Capacity at Ihovbor rose from 120MVA to 160MVA.
“With the recent upgrade, TCN has increased its capacity to wheel more bulk power to Benin DisCo for onward evacuation to its customers.
“The projects are part of the collaborative efforts of the World Bank and TCN Management to boost bulk power transmission nationwide”, its stated.